PMP備考每日試題(211102)


限時(shí)免費(fèi)領(lǐng)取,2022年度公益大課《巧用項(xiàng)目管理輕松突破職業(yè)瓶頸》,慧翔天地手把手帶你輕松學(xué)項(xiàng)目管理,從項(xiàng)目管理小白走向職場頂峰5天課程免費(fèi)學(xué),快樂成長,更有超低PMP?培訓(xùn)優(yōu)惠,還有豪禮贈(zèng)送,詳情可以直接點(diǎn)擊上方圖片進(jìn)入活動(dòng)報(bào)名頁。
每期慧翔天地小編都會附上5~10道PMP?綜合測試題,以幫助大家達(dá)到練習(xí)的效果,本期PMP試題答案會附加在下一期的結(jié)尾。大家如果想了解2022年P(guān)MP?考試報(bào)考流程、報(bào)考時(shí)間、報(bào)考要求、PMP?報(bào)考費(fèi)用、PMP?考試地點(diǎn)、PMP?成績查詢、PMP?報(bào)考資格測評等等均可訪問站內(nèi)進(jìn)行了解。
11、You are the project manager for the construction of a hog rendering plant.Local residents and environmental groups are opposed to this project.They have produced reams of data showing that the volume of entrails and carcasses burned at the site will cause noxious-and possibly toxic-fumes to which the residents will be exposed.They have threatened to take your company to court.You find you are spending most of your time trying to work with these groups to alleviate their concerns.After so much time and effort in these meetings,you convince management to move this project to a different site outside town.This is an example of which of the following risk responses?
A.Passive acceptance
B.Active acceptance
C.Mitigation
D.Avoidance
11、你是建設(shè)一個(gè)生豬養(yǎng)殖廠項(xiàng)目的經(jīng)理。當(dāng)?shù)鼐用窈铜h(huán)保團(tuán)體反對該項(xiàng)目。他們已經(jīng)提供了一系列數(shù)據(jù)顯示廠里焚燒的內(nèi)臟和豬尸體將產(chǎn)生有害的甚至有毒的氣體,對當(dāng)?shù)鼐用裼形:ΑK麄兺{要將公司告上法庭。你發(fā)現(xiàn)你的大量時(shí)間花費(fèi)在平息他們的擔(dān)憂。在花費(fèi)大量時(shí)間和精力之后,你說服管理層同意將項(xiàng)目遷至一個(gè)新的鎮(zhèn)外的廠址。這是以下哪種風(fēng)險(xiǎn)反應(yīng)的例子
A.被動(dòng)接受
B.主動(dòng)接受
C.緩解風(fēng)險(xiǎn)
D.回避風(fēng)險(xiǎn)
12、As manager of your organization’s project office,you often must decide which projects will receive additional resources.You also recommend which projects should be initiated,continued,or cancelled.One way to help you make these decisions is to
A.Determine an overall risk ranking for the project
B.Assess trends in quantitative risk analysis results
C.Prioritize risks and conditions
D.Assess trends in qualitative risk analysis results
12、作為你們公司項(xiàng)目辦公室的經(jīng)理你必須經(jīng)常判定哪些項(xiàng)目應(yīng)該得到額外的資源。你還要建議哪些項(xiàng)目應(yīng)該啟動(dòng)、繼續(xù)進(jìn)行或取消。有利于你做出這些決策的一個(gè)方法是
A.為項(xiàng)目明確一個(gè)整體風(fēng)險(xiǎn)級別
B.評估定量風(fēng)險(xiǎn)分析結(jié)果的趨勢
C.對各種風(fēng)險(xiǎn)和條件進(jìn)行排序
D.評估風(fēng)險(xiǎn)定性分析結(jié)果的趨勢
13、Which group has the responsibility to provide the resource for the quality management?
A.Project team members
B.Human resources
C.Functional organization
D.Management
13、下列哪一個(gè)群體有責(zé)任提供成功質(zhì)量管理所需的資源?
A.項(xiàng)目團(tuán)隊(duì)成員
B.人力資源部
C.職能型組織
D.管理層
14、Which of the following is correct for the WBS?
A.Work component descriptions are often collected in a WBS dictionary.
B.WBS is the input of defining scope.
C.The lowest level of WBS is work packages and cannot be further decomposed.
D.The work not being included in WBS may not be outside the scope of the project.
14、下列關(guān)于WBS的說法哪種是正確的?
A.工作組成描述常常在工作分解結(jié)構(gòu)詞匯表中進(jìn)行歸集
B.工作分解結(jié)構(gòu)是定義范圍的輸入
C.工作分解結(jié)構(gòu)較低層次是工作包而且不能再分解
D.工作分解結(jié)構(gòu)未包含的工作可能在項(xiàng)目范圍內(nèi)"
15、Which of the following is not an objective of a risk audit?
A.Confirming that risk management has been practiced throughout the project life cycle
B.Confirming that the project is well managed and that the risks are being controlled
C.Helping to identify the deterioration of the project’s value potential in its early stages
D.Ensuring that each risk identified and deemed critical has a computed expected value
15、以下哪項(xiàng)不是風(fēng)險(xiǎn)審計(jì)的目標(biāo)
A.確認(rèn)在項(xiàng)目生命周期內(nèi)始終實(shí)行了風(fēng)險(xiǎn)管理
B.確認(rèn)項(xiàng)目得到了良好管理,風(fēng)險(xiǎn)得到了控制
C.幫助識別項(xiàng)目早期的價(jià)值潛力的變壞情況
D.確保每個(gè)被識別和確認(rèn)的重大風(fēng)險(xiǎn)的預(yù)期價(jià)值得到計(jì)算
PMP備考每日試題(211101)點(diǎn)擊跳轉(zhuǎn)
(211101)答案
6、C
7、A
8、B
9、A
10、C

PDMA-NPDP?新產(chǎn)品開發(fā)專業(yè)人士認(rèn)證
PMI-PgMP?國際項(xiàng)目集管理認(rèn)證
PMI-PMP?國際項(xiàng)目管理認(rèn)證
信息系統(tǒng)項(xiàng)目管理師(軟考高項(xiàng))認(rèn)證
系統(tǒng)集成項(xiàng)目管理工程師(軟考中項(xiàng))認(rèn)證
項(xiàng)目管理專業(yè)人員能力評價(jià)(CSPM)
PMI-ACP?國際敏捷項(xiàng)目管理認(rèn)證
信息技術(shù)應(yīng)用創(chuàng)新人才評價(jià)(信創(chuàng)證書)