軟考備考每日試題(250619)


每期慧翔天地小編都會附上5~10道軟考綜合測試題,以幫助大家達(dá)到練習(xí)的效果,本期軟考試題答案會附加在下一期的結(jié)尾。大家如果想了解2025年軟考考試報(bào)考流程、報(bào)考時(shí)間、報(bào)考條件、報(bào)考費(fèi)用、軟考報(bào)考資格測評等等均可訪問站內(nèi)進(jìn)行了解。
軟考中高項(xiàng)備考刷題交流QQ群:221801769(點(diǎn)擊一鍵加群)
6、Estimating schedule activity costs involves developing an(1)of the costs of the resources needed to complete each schedule activity.Cost estimating includes identifying and considering various costing alternatives.For example,in most application areas,additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product operations.The cost estimating process considers whether the expected savings can offset the cost of the additional design work.Cost estimates are generally expressed in units of(2)to facilitate comparisons both within and across projects.The(3)describes the business need,justification,requirements,and current boundaries for the project.It provides important information about project requirements that is considered during cost estimating.
(1)A.accuracy B.approximation C.specification D.summary
(2)A.activity B.work C.currency D.time
(3)A.project scope statement
B.statement of work
C.project management plan
D.project policy
7、立項(xiàng)申請、初步可行性研究、詳細(xì)可行性研究、評估與決策是投資前時(shí)期的四個(gè)階段,其()是不可缺少的。
A.立項(xiàng)申請
B.初步可行性研究
C.詳細(xì)可行性研究
D.評估與決策
8、你正在管理一個(gè)公共項(xiàng)目。該項(xiàng)目牽涉所在城市所有居民的利益,是當(dāng)?shù)孛襟w和居民關(guān)注的熱點(diǎn)。他們想要了解項(xiàng)目的一切情況。針對這種情況,你會使用哪種溝通方法來發(fā)布項(xiàng)目的工作績效信息和工作績效報(bào)告?()
A.推式溝通
B.拉式溝通
C.互動溝通
D.書面溝通
9、在開發(fā)的軟件產(chǎn)品完成系統(tǒng)測試之后,作為最終產(chǎn)品應(yīng)將其存入(),等待交付用戶或現(xiàn)場安裝。
A.知識庫
B.開發(fā)庫
C.受控庫
D.產(chǎn)品庫
10、在規(guī)劃進(jìn)度管理過程中,可能會召開()會議來制訂進(jìn)度管理計(jì)劃。
A.溝通會議
B.風(fēng)險(xiǎn)評估會議
C.規(guī)劃會議
D.質(zhì)量保證會議
軟考備考每日試題(250618)點(diǎn)擊跳轉(zhuǎn)
(250618)答案
1、D
2、A
3、A
4、D
5、A